Just an update to let you know that the new green drainage outlet installation for #10 green was completed last Thursday afternoon and it is functioning very well.

Typically, whenever we put a shovel in the ground on this property we end up uncovering other drainage issues and this proved to be the case again this time around. That being said, it has been buttoned up and the green was reopened for play immediately. The drainage lines have been filled to the surface with sand and will need to remain “turf-free” for a few weeks to allow them to settle as much as possible and then they will be topped off and sodded.  Also, once we are fully confident that the catch basin won't settle any further, we will trim it down to just below ground level.

Here are a couple pics of the project: