#18 Green Slit Drainage (update #2)

The slit drainage installation on #18 is going smoothly, but the 4+ of hours of work lost from yesterday's rain and this morning's frost have us slightly behind schedule.  We now expect the project to be completed on Sunday with the green reopening sometime on Monday.

Here are some more pics of the install from today:

completed slits

completed slits

back right slits ready to be trenched

progressing along nicely

previous aerification holes exposed when sod is removed