The slit drainage installation on #18 green is now underway. The cancelled ferries on Wednesday forced us to start a day later as the TDS labour crew was stuck on the island. This morning's frost has delayed us again, but we still anticipate the project to be completed on Saturday with the green reopening on Sunday.
Here are some pics of the installation:
|
irrigation marked and plywood used to minimize surface disruption |
|
collector line installation underway |
|
collector line installation |
|
sod carefully removed for slits and set aside |
|
sod removal |
|
sod removal |
|
aerification evidence in the sod |